Hi All,
I have a doubt regarding budget check warning message.
Distributable budg = Rs. 100, Assigned = Rs 92 ( divided in 8 service PR of value 10 and 9th PR with value 12)
when i created a project with same budget and commitments.
and tried to release NTW without saving service PRs before.
System gives warning message
"line item 0010 budget almost exhausted" after pressing enter
"line item 0020 budget almost exhausted" after pressing enter
"line item 0030 budget almost exhausted" after pressing enter
"line item 0040 budget almost exhausted" after pressing enter
"line item 0050 budget almost exhausted" after pressing enter
"line item 0060 budget almost exhausted" after pressing enter
"line item 0070 budget almost exhausted" after pressing enter
"line item 0080 budget almost exhausted" after pressing enter
"line item 0090 budget almost exhausted" after pressing enter
After that i created a project with same service activity(as mentioned sbove) and saved the project.
then i released the NTW and tried to save the project
System gives the warning message "budget almost exhausted" only once and i saved the project.
My question is
1. Why system is giving warning message for each line item one by one when i have not saved the activities before and released the NTW??
Its requires effort for ignoring warning message for each line item.
Waiting for your valuable inputs.
Regards
Sachin