Hi,
Thanks for the reply.
It is not feasible for us to use either NEUPL or a New MRP type with the setting.
What we are Doing is:
As the batch MRP run for everyday is not considering some materials for MRP run for some days as there is no indicator updated in the planning file entry because of no MRP relevant changes,
Then we have run the MRP manually(with NETCH) in md02 so that planned orders are pushed after planning time fence.
What we didn't understand is:
As there is no MRP changes then why the material has been considered for the manual MRP run(with NETCH) Md02 and planned order has been pushed?
This is because of MRP type p3?
please help me in this issue.
Thanks in advance,
phani