Hi Ali,
I have never come across such scenario where this indicator gets automatically selected while creating production order manually. Generally you maintained external processing information at master data level (Routing) and same gets copied to production order at the time of order creation. Moreover, if you are adding new operation manually in production order with external processing control key, then you have to enter details manually. Are you converting planned order to production order.