Hello,
This could happen if for the operation, the duration is defined in a unit >= day. For the capacity requirements (PM: Work) it is defined in a unit < day.
For example, duration = 0.5 days, work = 4 hours.
Please check available capacity of work center in IR02?
Best Regards,
R.Brahmankar