Sorry Ajay seems some mis communication from myside , I think in the begnining of the query I have mentioned ML is not in scope and not used ... I think I need CON2 but
I am getting error
Production order with an actual activity update.
Message no. KA465
Diagnosis
In the plan, activity updates are relevant to price determination. The system uses a multi-level price determination in actual costing. In actual costing, the system already debited materials and credited the cost centers, and vice versa.
System Response
The system does not execute revaluation, to avoid posting the credits and debits twice.
Besides the plant and ccode combination in OMX1 tcode ML Acitve Check is blank and price determination is blank as well